Local News
City of Fond du Lac – Weekly Construction Update
The City of Fond du Lac is providing a weekly update on construction projects located within the corporate boundary. The Weekly Construction Updates and Construction Map are posted on the City’s Website at www.fdl.wi.gov.
Cottage Avenue – E. Division Street to Maple Avenue
Schedule: April through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
November 3 to November 7: The concrete contractor will be onsite to begin slipping curb and gutter and forming and pouring sidewalk and driveway aprons.
Traffic Impacts: Cottage Avenue is closed to traffic from E. Division Street to Maple Avenue. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades.
Oaklawn Avenue – E. Division Street to E. Merrill Avenue
Schedule: April through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
November 3 to November 7: The grading contractor will continue road excavation to subgrade and base aggregate placement. Electrical contractor will install conduit mid-week.
Traffic Impacts: Oaklawn Avenue is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades.
Traffic Impacts: Oaklawn Avenue is closed to traffic from E. Division Street to Merrill Avenue. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades.
E. Merrill Avenue – Cottage Avenue to DeNeveu Creek
Schedule: April through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
November 3 to November 7: Concrete contractor may begin working in the intersection of Merrill Ave and Cottage Ave.
Traffic Impacts: E. Merrill Avenue is closed to traffic from Cottage Avenue to DeNeveu Creek. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
South Street – Linden Street to S. Main Street
Schedule: October through November
Description: The project includes gas main and service relocations, reconstruction of storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
November 3 to November 7: The grading contractor will begin road excavation to subgrade and base aggregate placement mid-week.
Traffic Impacts: South Street is closed to traffic from Linden Street to S. Main Street. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
W. 11th Street – Linden Street to S. Main Street
Schedule: October through November
Description: The project includes gas main and service relocations, reconstruction of storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
November 3 to November 7: The grading contractor will begin road excavation to subgrade and base aggregate placement at the end of the week.
Traffic Impacts: W. 11th Street is closed to traffic from Linden Street to S. Main Street. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Montana Street – Lake Street to N. Hickory Street
Schedule: October through November
Description: The project includes gas main and service relocations, reconstruction of storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.
November 3 to November 7: The directional drilling contractor will begin installing water main at the start of the week.
Traffic Impacts: Montana Street is closed to traffic from Lake Street to N. Hickory Street. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.