The City of Fond du Lac is providing a weekly update on construction projects located within the corporate boundary. The Weekly Construction Updates and Construction Map are posted on the City’s Website at www.fdl.wi.gov.
All anticipated construction activities are weather dependent.
Stow Street Bridge
Schedule: June 17 through September 15
Description: 0.034-mile project involving removals, grading, aggregate, asphalt pavement, structure replacement, curb and gutter, concrete sidewalk, storm sewer, erosion control, traffic control, and restoration.
June 29 to July 2: Pheifer will finish removing existing structure. The contractor will then finish driving piling and begin forming west abutment.
Traffic Impacts: Stow Street is CLOSED to pedestrian and vehicle traffic through the duration of the project.
Pioneer Road – CTH V to Fond du Lac Avenue
Schedule: April through October
Description: Fond du Lac County Highway Dept in partnership with the City of Fond du Lac are reconstructing this segment of Pioneer Road. The construction includes common excavation, sanitary sewer, watermain, storm sewer, concrete sidewalk and curb & gutter, asphalt roadway, roadway lighting, permanent signing, and other incidentals.
June 29 to July 2: Communication utilities will continue their relocation work.
Traffic Impacts: Pioneer Road between CTH V and Fond du Lac Avenue is closed to traffic. Residents may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
CTH K – STH 23 to USH 151
Schedule: May through August
Description: Fond du Lac County Highway Dept in partnership with the City of Fond du Lac are reconstructing this segment of CTH K. The construction includes common excavation, sanitary sewer, watermain, storm sewer, concrete curb & gutter, asphalt roadway, permanent signing, and other incidentals.
June 29 to July 2: The County will continue constructing the storm sewer between Hunter Ave and the Agnesian Hospice Home.
Traffic Impacts: CTH K between STH 23 and USH 151 is closed to traffic. Residents may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Western Avenue – Military Road to Main Street
Macy Street – Court Street to Western Avenue
Schedule: April 27 through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting, traffic signals and restoration/landscaping.
June 29 to July 2: The concrete contractor will continue paving concrete pavement and slipform the curb on Western Ave and Macy Street.
Traffic Impacts: Western Avenue is closed to traffic. Residents, business owners, jurors and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Traffic Impacts Macy Street is closed to traffic at Court Street. Macy Street will be two-way traffic from Second Street to Court Street.
Ruggles Street – S. Hickory Street to Mary’s Avenue
Schedule: May through July
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting, and restoration/landscaping.
June 29 to July 2: The electrical contractor will begin installing conduit for lighting. Intercon will continue with gas main work for Alliant Energy.
Traffic Impacts: Ruggles Street is closed to traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Morris Street – W. 9th Street to W. 12th Street
Schedule: May through September
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting, and restoration/landscaping.
June 29 to July 2: The utility contractor continues with water main installation and water and sanitary lateral installations.
Traffic Impacts: Morris Street is closed to traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.