Weekly construction report from the City of Fond du Lac

City of Fond du Lac – Weekly Construction Update

The City of Fond du Lac is providing a weekly update on construction projects located within the corporate boundary. The Weekly Construction Updates and Construction Map are posted on the City’s Website at www.fdl.wi.gov.

All anticipated construction activities are weather dependent.

Lakeside Park Pedestrian Bridge Replacement – Oven to Fountain Island

Schedule: September 16 through November 15, 2024

Description: Construction includes removal of the existing wood bridge structure, pouring new concrete abutments and setting a new steel truss bridge. Site grading, restoration and asphalt pedestrian path will be replaced.

November 4 to November 8: The project is on hold awaiting delivery of the bridge in mid to late December.

US 45 Improvement in Fond du Lac County

Schedule: August 26th to Early November

Description of work: The work under this contract shall consist of asphalt paving, beam guard replacement, culvert replacement, pavement marking, and all incidental items.

November 4 to November 8: Beam guard replacement will be completed along with pavement marking

Traffic impacts: US 45 is open to traffic. Work will be conducted under lane closures with flagging operations.

S Military Road – Superior Street to Hickory Street

Schedule: July 2024 through November

Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting and restoration/landscaping.

November 4 to November 8: Weathering pending, the concrete contractor will continue placement of curb on pavement that has cure.

Traffic Impacts: S Military Road is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades.